The "To-Do" List: Completion Time Frame May 16th - May23rd
May 16th(old house):
- Install 3 trees on the front lawn
- Rake the dirt even and remove large debris
-Seed the area with grass
-Burn all the wood and stumps
- Check the Truck front end and order the parts for Sunday
-
-
- Check the Truck front end and order the parts for Sunday
May 17th(old house):
- Fix the deck
- Spread the triple mix on the front lawn
-Install last 5 trees around the garage on the slope
- Order Siding for the garage
-
- Order Siding for the garage
May 18th(old house):
- Finish painting all the outside windows
- Work on the Jetta
May 19th(old house):
- Work on the Jetta
- Stain the deck
- Move all large car parts to the new house
- Weed and Mulch the flower beds
May 20th(old house):
- Finish up the flower beds and the clean up around the house
-Move more stuff to the new house
- Move Boss's house and seed the area with grass
-
May 21st(new house):
- Pick up the windows - Install 4 windows
May 22nd(old house):
- Finish installing the windows
-Finish up the yard
- Work on the mud room
- Finish staining all the trim and baseboards
-
- Work on the mud room
- Finish staining all the trim and baseboards
May 23rd(old house):
- Pick up the siding
- Wrap the garage
- Start installing the siding
- Wrap the garage
- Start installing the siding
May 24th:
- CALL ME TO SEE IF I AM STILL ALIVE :)
As you can see most of the work completed was all YARD work! Seriously by the end of the five days I was perfectly happy not looking at a flower bed and just weed whacking!
Can't wait till next week to post an update about the windows being installed! So exciting, really looking forward to seeing the new house change so quickly!